Gate G-PPE: Personal Protective Gear
GATE 01
Mandatory equipment inspection: IS-certified hard hat, anti-fog eye protection with side shields, EN 388 Level-4 cut-resistant mechanic gloves, and 11kV dielectric steel-toe safety footwear.
Standard: IS 2925 (Head) • EN 166 (Eye) • IS 15298 (Footwear)
Gate G-ELEC: Safe Isolation & LOTO
GATE 02
Strict 5-step statutory isolation drill: Identify isolation point → Disconnect → Secure with Lockout/Tagout hasp → Prove dead using proving unit and CAT-III 600V meter → Earth where required.
Standard: IS 5216 (Safety Procedures in Electrical Work) • NFPA 70E Protocol
Gate G-HOT: Oxy-Fuel & Brazing Safety
GATE 03
Pre-ignition cylinder inspection, dual flashback arrestor verification (torch and regulator ends), nitrogen sweep pressure regulation (2โ3 PSI), fire blanket screening, and 60-minute post-hot-work fire watch.
Standard: IS 818 (Safety & Health Requirements in Electric and Gas Welding)
Gate G-REF: Refrigerant Recovery & Pressure
GATE 04
Zero atmospheric venting policy. Recovery machine dual-hose connection, recovery cylinder tare weight limits (80% fill limit by weight), and 450 PSI nitrogen standing decay leak testing before charging.
Standard: ASHRAE 15 & 34 (Refrigerant Safety Classifications) • EPA Section 608 Rules